During their April 29, 2013 work session, Chapel Hill Town Council continued to discuss and refine a process plan and schedule for Obey Creek and S15-501.
The process consists of two phases – an Exploratory phase during which a team of consultants will facilitate a planning process and, if the resulting project plan is deemed appropriate for a Development Agreement, a Negotiation and Implementation phase will follow.
Focus during the council work session was on a fleshed out plan for the Exploratory Phase which is the product of a collaborative effort between town staff, East West Partners and two community members.
The new plan calls for a six to nine month public engagement process that includes many opportunities for public engagement. However, the plan provides no formalized mechanism for citizen inclusion in decision-making or process leadership.